Delivery Record of Automotive Sensor Housing Mold from Drawing to Mass Production

2026-11-20 16:19:13 Injection Mold

Automotive sensor housings are precision electronic structural parts working in harsh environments such as engine compartments and chassis. They require stable dimension, reliable sealing, heat resistance, oil resistance and insulation. The whole development process follows IATF16949, with traceable records for every milestone. PPAP approval is mandatory before mass production release. Unlike ordinary consumer plastic parts, sensor housings often contain inserts, sealing grooves, positioning holes, snaps and terminal sockets with tight tolerance. Any mold fluctuation will interfere with sensor signal collection and sealing performance, so milestone control is the core of project delivery.

1. Drawing receiving and DFM risk review

The project starts with 3D models, 2D engineering drawings and special characteristic list. Engineers check marked tolerance, material grade, temperature resistance, sealing surface requirement and special specifications. Common materials are glass-filled PA66, PBT and LCP. Glass fiber reinforced materials are prone to warpage, float fiber and cavity abrasion. The review focuses on wall thickness distribution, insert loading method, sealing groove draft angle, vent position and gate feasibility. Identify thick sections, weld lines and sharp stress points, and issue DFM report with structural optimization proposals such as fillet adjustment and insert positioning step. FMEA is launched at the same time to define key dimensions for later monitoring. Mold design can only start after both sides sign off on drawings and DFM plan.

injection mould

2. Mold flow analysis and mold structural design

Mold flow simulation runs on confirmed product data to predict filling sequence, pressure distribution, temperature field, fiber orientation and shrinkage deformation. Most sensor housing molds adopt 2-cavity or 4-cavity layout, and multi-cavity balance is the key to avoid dimension difference. Submarine gate or valve hot runner is preferred, preventing gate marks on sealing and reference surfaces. Cooling channels are arranged around sealing surfaces, inserts and thin-wall zones. Uneven cooling of glass-filled material easily causes warpage, so channels should be close to cavity surface to reduce temperature difference. Anti-reverse and anti-shift structures are designed for inserts. Slides and lifters are reserved with enough vents. Wear-resistant pre-hardened steel or stainless steel is selected for sealing cavity to resist long-term scouring of glass fiber. After design completion, assembly drawings, component drawings, BOM and electrode drawings are submitted for customer review.

3. Steel procurement, machining, assembly and internal inspection

Steel is purchased according to specified grade with material certificate and hardness test report. Hardness recheck is carried out after incoming. Machining follows the sequence of rough CNC, heat treatment, finish machining, EDM, wire cutting, polishing and assembly. Tight tolerance is controlled for sealing surfaces, reference surfaces and inserts. Parting surface and sealing surface are well lapped to avoid flash affecting sealing. Empty mold test is done after assembly to check slide and lifter movement. Cooling circuit hydraulic pressure test confirms no leakage. Internal inspection checks cavity dimension, insert clearance, ejection stroke and vent depth before T1 trial.

4. Multi-round mold trial, revision and dimension verification

T1 trial mainly verifies filling status with conservative parameters. Samples are fully measured, focusing on special characteristics of sealing groove, terminal hole and assembly benchmark. Common defects after T1 include dimension drift, warpage and float fiber. Mold revision is carried out according to inspection results to adjust cooling, vent and gate. T2 trial optimizes process window and stability under different mold and melt temperatures. T3 is the critical milestone, using formal raw material and inserts for continuous sampling. Process capability Cpk of key dimensions must meet customer standard. Appearance, sealing and assembly matching are validated. All trial records, parameter sheets, photos and CMM reports are archived.

injection mould

5. PPAP document submission and customer approval

After T3 sample confirmation, PPAP package is organized, including design record, engineering change record, DFMEA, PFMEA, control plan, dimension report, material certificate, IMDS, initial process capability study and tool inspection record. The customer may conduct on-site audit for mold status, process control and traceability system. Mass production release is allowed only after PPAP approval. Spare parts including ejector pins, sleeves and slider inserts are counted and delivered.

6. Pilot run, mass production launch and handover

Pilot production is arranged after PPAP approval, following the control plan with first article, in-process and last article inspection. Mold stability is verified through continuous production, monitoring cavity wear and vent blockage. After pilot run passes, the mold is formally handed over with complete drawings, electrode files, process card, maintenance specification and inspection records. Technical support is provided in the early stage of mass production to handle mold wear and parameter drift. The value of this delivery record is to build traceable evidence for automotive audit. It helps locate problems quickly during engineering change, mold repair and annual audit, supporting long-term stable production of sensor housings.

injection mould